Red Bull HQ
London, UK

Project outline
Fit out for the UK HQ of the energy drinks giant. The Client, Red Bull, had a set moving in date that drove the programme – 7 months from appointment to completion.
The top three floors of the building adjacent to Soho Square were re-modelled to emphasise the branding of the company.
The intermediate slabs were opened to accommodate additional stairs, video wall and a slide connecting the floors demonstrating the speed and vitality promoted by Red Bull.
The top three levels of the building were connected by the inclusion of internal stairs and a giant slide between the floors to promote staff visual communication.
Short listed for the BCO 2006 Small Project Prize.
Contract value
£1,500,000
Key features
- Design extensively supported branding
- Compressed programme - start of design to completion in 9 months
- Construction carried out in an occupied building
- Utilised slab openings utilised to release heat and reduce loads
Appointment
- Building Services